Sanjauli residents' protest against NHAI's twin tunnels in Shimla

Rally called for 16 October

Where
Sanjauli (Shanti Vihar ward), Bhatta-Kufar and Chalaunthi, above the NHAI twin-tunnel alignment in Shimla, Himachal Pradesh
Since
19 September 2026, when the district administration directed NHAI to stop tunnel work after cracks appeared in buildings, Hindustan Times reported
Next date
16 October: a protest rally in Sanjauli called by the Twin Tunnel Affected Joint Struggle Committee and the Shimla Nagrik Sabha. No venue or time has been reported.
Latest
11 October: a joint meeting of the two groups decided on the rally and opposed the tunnel outright, Himachal Scape, HimbuMail and Hindusthan Samachar report.

What NHAI says What is disputed or unconfirmed Sources

In short

NHAI is building twin tunnels of about 2.712 km between Bhatta-Kufar and Chalaunthi in Shimla for the Kaithlighat-Dhalli four-lane highway, The News Himachal and Amar Ujala report. After cracks appeared in buildings in the Shanti Vihar ward of Sanjauli, the district administration directed NHAI on 19 September to stop tunnel work, Hindustan Times reported. NHAI plans a condition survey of about 500 buildings near the alignment before work resumes, according to The News Himachal; that figure is the survey's scope, not a count of damaged houses. On 11 October a residents' struggle committee and a citizens' body called a protest rally in Sanjauli for 16 October and demanded that the tunnel be stopped, Himachal Scape reports.

Key dates (oldest first)

  1. 19 Sep Cracks reported; work halted
  2. 1 Oct Residents meet MP; IIT study
  3. 9 Oct Minister meets building owners
  4. 10 Oct NHAI survey plan reported
  5. 11 Oct Rally called for 16 October
  6. 16 Oct Rally planned in Sanjauli

What is being built?

The project is a pair of parallel tunnels of about 2.712 km between Bhatta-Kufar and Chalaunthi, part of the Kaithlighat-Dhalli four-lane highway built by the National Highways Authority of India (NHAI), according to The News Himachal and Amar Ujala; the Hindustan Times PTI report calls it the Parwanoo-Shimla four-lane. About 700 metres had been completed, the two outlets report. About 500 houses, home to thousands of people, stand above or near the alignment across Bhatta-Kufar, Shanti Vihar (Sanjauli) and Chalaunthi (The News Himachal, Amar Ujala).

What do residents say happened?

Cracks appeared on floors and walls of at least seven buildings next to the cemetery in the Shanti Vihar ward, Hindustan Times reported on 20 September. On Saturday 19 September a district team led by an Additional District Magistrate (ADM) visited, and the administration directed NHAI to stop tunnel work. Hindustan Times later reported NHAI officials confirming that work stopped after cracks were reported on 19 September. Amar Ujala says work was halted after cracks appeared in 10 houses in Shanti Vihar. Counts of damaged houses differ widely; see the disputed points.

At that time residents and a local councillor said blasting was being done at night beneath the locality and asked for a halt until a geological study was done, according to Hindustan Times. A former Shimla mayor said the tunnel passes beneath 250 to 300 buildings and demanded compensation (Hindustan Times).

On Tuesday 6 October affected families from Sanjauli, Shanti Vihar, Bhatta-Kufar, Dhalli and Chalaunthi told the press that cracks had appeared in several houses and claimed that hundreds of homes could be at risk, Hindusthan Samachar and ABP Live report. They said they had not been properly informed or compensated, and that some people had been living away from their homes for about 18 months. They also said a High-Powered Committee set up by the Supreme Court had inspected the project and told them it would report to the High Court. That is the families' account; we did not read any report by the committee.

What does NHAI say?

  • Precautions and blasting: NHAI said all necessary precautions were taken "in accordance with established engineering practices", and that blasting for the tunnel was suspended in November 2025 and none has been done since, according to Hindustan Times and Himachal Scape. Hindustan Times reports that NHAI installed vibration-monitoring equipment and videographed buildings.
  • Geotechnical study: at a meeting on 1 October, NHAI officials said work had stopped and an IIT Roorkee team was doing a geotechnical study, whose findings would be considered before further action (Hindustan Times).
  • Building survey: NHAI has decided to carry out a condition survey of about 500 houses within the tunnel's zone of influence between Bhatta-Kufar and Chalaunthi, with videography and photography of each building, before work resumes; buildings in poor condition would be repaired and weak ones strengthened, The News Himachal and Amar Ujala reported on 10 October.
  • The Project Director: Anand Dahiya, Project Director for the Parwanoo-Shimla four-lane, told Amar Ujala that an IIT team was investigating the causes of the cracks in Shanti Vihar, that cracked buildings would be restored, and that tunnelling would resume only after people's trust was won and they were satisfied. The News Himachal carries the same remarks.

What have elected representatives and officials said?

  • Shimla MP Suresh Kashyap met residents and NHAI officials in Sanjauli on Thursday 1 October. Residents alleged that the tunnel did not follow the earlier survey and asked for the original survey, the present alignment and the construction method to be examined and explained publicly; they also raised the lack of a public hearing and concern for the Lakshmi Narayan Temple (Hindustan Times, PTI). Kashyap asked why the survey or alignment had been changed "if such a change had indeed taken place", and said construction should go ahead only after safety concerns were addressed.
  • Panchayati Raj Minister Anirudh Singh met about 300 building owners and committee members at a community hall on Friday 9 October, with ADM (Protocol) Gyan Sagar Negi, and assured them of a meeting with Chief Minister Sukhvinder Singh Sukhu soon, according to The News Himachal and Amar Ujala. Owners asked for the tunnel to be stopped, for the four-lane to follow the original survey, and for a compensation process (Amar Ujala). The ADM said restoration and safety work on buildings is being given to the Public Works Department, with a proposal sent to NHAI (Amar Ujala). We found no report of the promised meeting with the Chief Minister.

What do the protesters want?

On Sunday 11 October a joint meeting in Sanjauli of the Twin Tunnel Affected Joint Struggle Committee (Sangharsh Samiti) and the Shimla Nagrik Sabha decided on a protest rally on 16 October and opposed the tunnel outright, according to Himachal Scape, HimbuMail and Hindusthan Samachar. They said the rally would be non-political, open to all regardless of caste, religion or party, and the start of a wider campaign. Their demands, as reported by the three outlets:

  • Stop the tunnel: an immediate halt to the twin-tunnel work.
  • Public hearing: a fresh, transparent public hearing in the affected areas.
  • Inquiry report: public release of the administration's inquiry report.
  • Independent survey: a survey of affected areas by government and recognised expert bodies; HimbuMail adds "rather than NHAI-appointed agencies".
  • Compensation: for families whose houses collapsed or cracked, and settlement of pending claims.

Himachal Scape adds a demand to disclose the technical justification and extra cost of any change of alignment, since land had reportedly been acquired and compensation paid on the basis of an earlier survey.

Speakers at the meeting said four-lane construction had damaged homes and farmland in Chamiyana and Matu Colony without adequate compensation (Himachal Scape, Hindusthan Samachar), and that tenants were leaving cracked buildings, hurting landlords' rental income and local business (Himachal Scape, Hindusthan Samachar, HimbuMail). They compared the situation with land subsidence in Joshimath; HimbuMail quotes Nagrik Sabha office-bearers saying, "We will not allow Sanjauli to turn into another Joshimath." An environmental expert at the meeting said the area is geologically sensitive and residents were not consulted (Himachal Scape, Hindusthan Samachar, HimbuMail). These are the speakers' claims.

What is the timeline?

Newest first; the planned rally is marked. Dates come from the sources listed at the end.

  1. Planned: protest rally in Sanjauli (venue and time not reported).
  2. Joint meeting of the Struggle Committee and the Shimla Nagrik Sabha calls the rally.
  3. The News Himachal and Amar Ujala report NHAI's plan to survey about 500 buildings before resuming work.
  4. Minister Anirudh Singh meets about 300 building owners and committee members.
  5. Affected families speak to the press.
  6. Residents meet MP Suresh Kashyap and NHAI officials; NHAI says an IIT Roorkee team is studying the site.
  7. Cracks reported in Shanti Vihar; the administration directs NHAI to stop tunnel work.

What is disputed or unconfirmed?

The figures for damaged and at-risk buildings depend on who is speaking, and residents' and NHAI's accounts of blasting and the alignment differ. We show each version with its source.

Disputed or unconfirmed points and what each source says
PointWhat the sources say
Damaged houses Figures differ "At least seven buildings" and "more than half a dozen" (Hindustan Times, 20 September; "at least seven" again on 2 October). 10 houses in Shanti Vihar (Amar Ujala's own text) and 15 houses (the Struggle Committee and a councillor, in the same Amar Ujala report). "Cracks in several buildings" (Hindustan Times PTI report, The News Himachal). "Structural cracks in more than 500 houses", which residents say they told the Supreme Court-appointed panel (HimbuMail only). NHAI's "about 500 houses" (The News Himachal, Amar Ujala) is the number of buildings to be surveyed, not a count of damage.
Buildings at risk Figures differ 250 to 300 (a former Shimla mayor, Hindustan Times); about 300 (a councillor, Hindustan Times and Amar Ujala); "hundreds" (affected families, Hindusthan Samachar); "the entire Sanjauli township" (organisers, HimbuMail).
Night blasting Accounts differ Residents say blasting was being done at night (Hindustan Times). NHAI says blasting was suspended in November 2025 and none has been done since (Hindustan Times, Himachal Scape). Unresolved in the sources we read.
Change of alignment Alleged Residents allege the alignment departed from the earlier survey without public notice (Hindustan Times PTI report, HimbuMail, Himachal Scape). The MP asked why it had changed "if such a change had indeed taken place" (Hindustan Times). Himachal Scape reports NHAI saying the revised alignment was covered by the required environmental approval. We read no NHAI document.
Committee name Spelling varies Twin Tunnel Affected Joint Struggle Committee (Himachal Scape); Twin Tunnel Affected Joint Action Committee (Sanyukt Sangharsh Samiti) (HimbuMail); Four-Lane Twin Tunnel Affected Struggle Committee (The News Himachal); Twin Tunnel Affected Sangharsh Samiti (Hindustan Times PTI report). Himachal Scape calls the Shimla Nagrik Sabha the "Shimla Citizens' Assembly".
Rally venue Unconfirmed The 11 October reports imply the rally is in Sanjauli, but none gives a venue or time.

Labels: Figures differ sources give different numbers. Accounts differ the parties or outlets give differing versions. Alleged a claim by one side that we have not seen verified. Unverified reported but not confirmed in the sources we read. One source only one outlet reports it. Unconfirmed an outcome or fact we could not establish. Spelling varies outlets write a name differently.

What happens next?

The Struggle Committee and the Shimla Nagrik Sabha have called a protest rally in Sanjauli on 16 October; no venue or time has been reported. NHAI plans its building survey before work resumes (The News Himachal, Amar Ujala), and its Project Director told Amar Ujala that tunnelling would resume only after people's trust was won. The meeting with Chief Minister Sukhvinder Singh Sukhu promised on 9 October had not been reported in the sources we read. We will update this page after 16 October.

Sources

Accessed 12 October 2026. The tag shows how much of each source we read: in full, only in part (for example a paywalled or cut-off article), or not at all.

  1. Himachal Scape, "Negligent tunnelling sparks public mobilisation in Shimla, protest rally on October 16", 11 October 2026. Read in full
  2. HimbuMail, "Fearing Joshimath-Like Catastrophe, Sanjauli Residents Call for Mass Protest on October 16 to Halt NHAI's Fourlane Twin Tunnels Project", 11 October 2026. Read in full
  3. Hindusthan Samachar (Hindi), "संजौली में ट्विन टनल के विरोध में 16 अक्टूबर को रोष रैली, निर्माण बंद करने की मांग", 11 October 2026. Read in full
  4. Janta Se Rishta (Hindi), "संजौली में ट्विन टनल निर्माण बंद कराने की मांग, 16 अक्टूबर को प्रदर्शन", 12 October 2026. Read in full Same text as the Hindusthan Samachar report; not cited separately.
  5. The News Himachal, "NHAI to Survey 500 Houses Before Resuming Shimla Twin Tunnel Work", 10 October 2026. Read in full
  6. Amar Ujala, Shimla (Hindi), "कैथलीघाट-ढली फोरलेन प्रोजेक्ट: भट्ठाकुफर-चलौंठी टनल निर्माण से पहले अब भवनों का होगा सर्वेक्षण", 10 October 2026. Read in full
  7. Hindusthan Samachar (Hindi), "शिमला में ट्विन टनल निर्माण से सैकड़ों घरों पर खतरे का दावा, प्रभावितों ने मांगा उचित मुआवजा", 6 October 2026. Read in full
  8. ABP Live (Hindi), "शिमला ट्विन टनल से घरों में आई दरारें? प्रभावितों ने जताई गंभीर चिंता", 7 October 2026. Read in full Same content as the Hindusthan Samachar report of 6 October.
  9. Hindustan Times, "Shimla: IIT experts start survey, twin-tunnel work on hold: NHAI", 2 October 2026. Read in full
  10. Hindustan Times (PTI), "Construction of Chalonthi-Bhattakufar twin tunnel not aligned with earlier survey: Shimla residents", 2 October 2026. Read in full
  11. Hindustan Times, "Shimla: Admn directs NHAI to halt 4-lane project after buildings develop cracks", 20 September 2026. Read in full
  12. Himachal Scape, "NHAI rebuts negligence charge as recurring subsidence puts Bhattakufar-Dhalli tunnel project under scrutiny", 20 September 2026. Read in full Used only for NHAI's statement and its position on the alignment.
  13. An MSN copy of a Hindi report of 20 September, 20 September 2026. Not read Blocked.
  14. Agency copies on Latestly (ANI) of 21, 22 and 23 September, including a party statement; The News Mill (19 and 21 September); Asianet Newsable (21 September); Dainik Jagran (1 October); Divya Himachal, 19 September to 1 October 2026. Not read Not opened.
  15. The Tribune and The Times of India. Not read No article found in The Tribune; The Times of India not searched under our source rules.

Frequently asked questions

Is work on the Sanjauli twin tunnels stopped?

Yes, according to the reports we read. The district administration directed NHAI to stop tunnel work on 19 September (Hindustan Times), and NHAI says it will survey about 500 buildings before work resumes (The News Himachal, Amar Ujala).

Are 500 houses cracked in Sanjauli?

Not on the evidence we read. The "about 500" figure from NHAI is the number of buildings to be surveyed near the alignment (The News Himachal, Amar Ujala). Reported counts of damaged houses range from at least seven (Hindustan Times) to 10 (Amar Ujala) or 15 (the Struggle Committee's account); HimbuMail reports residents saying more than 500 houses have structural cracks, a claim in one outlet only.

When is the Sanjauli protest rally?

The Twin Tunnel Affected Joint Struggle Committee and the Shimla Nagrik Sabha have called it for 16 October in Sanjauli, according to Himachal Scape, HimbuMail and Hindusthan Samachar. No venue or time has been reported.

Spotted an error, or a source we missed? Email a correction with the source that shows it. See how we handle corrections. Back to top