Short answer
Not where the Supreme Court’s 2024 directions apply. They say no demolition should happen without a prior show cause notice, then a personal hearing and a final order. Notice time is the local law’s or 15 days, whichever is later. The directions do not cover unauthorised structures in public places, such as roads, or court-ordered demolitions. Local laws differ.
This guide is general information, not legal advice. It describes the Supreme Court’s 2024 demolition directions, some local laws and what courts have said. It does not say whether any demolition is lawful, and it does not tell anyone what to do. We read the texts on 26 and 27 October 2026.
Can authorities demolish a house or shop without notice?
Not where the Supreme Court’s directions of 13 November 2024 apply. Their first notice direction, A(i), says:
No demolition should be carried out without a prior show cause notice returnable either in accordance with the time provided by the local municipal laws or within 15 days’ time from the date of service of such notice, whichever is later.
The same paragraph lists cases the directions do not cover, such as unauthorised structures in public places and court-ordered demolitions. Local laws also set their own notice rules. So the answer depends on the place, the structure and the law used.
The judgment is In Re: Directions in the matter of demolition of structures, 2024 INSC 866. It was given by Justices B.R. Gavai and K.V. Viswanathan. Paragraph 90 says the directions were issued "in exercise of our power under Article 142 of the Constitution". The judgment does not ban demolitions. It sets steps and says where they do not apply.
Why did the Supreme Court give these directions?
Paragraph 1 says the petitions raised the grievance of citizens "whose residential and commercial properties have been demolished by the state machinery, without following the due process of law, on the ground of them being involved as an accused in criminal offences."
The court’s order of 2 September 2024, quoted in paragraph 5, records the other side. It says: "The position is disputed by the State of Uttar Pradesh and an affidavit has been filed that the immovable properties can be demolished only in accordance with the procedure prescribed by law."
Paragraph 12 says the question was "as to whether the properties of the persons, who are accused of committing certain crimes or for that matter even convicted for commission of criminal offences, can be demolished without following the due process of law or not?" The 2 September 2024 order also said the court proposed guidelines on a "Pan-India Basis". Paragraph 90 gives one reason: "We are also of the view that even after orders of demolition are passed, the affected party needs to be given some time so as to challenge the order of demolition before an appropriate forum."
What steps did the Supreme Court set?
Paragraph 91 lists the steps under headings A to E. In short:
- A. Notice. A(i) is quoted above. A(ii) says: "The notice shall be served upon the owner/occupier by a registered post A.D. Additionally, the notice shall also be affixed conspicuously on the outer portion of the structure in question." A(iii) says: "The time of 15 days, stated herein above, shall start from the date of receipt of the said notice."
- What the notice must say. A(v) lists "the nature of the unauthorized construction", "the details of the specific violation and the grounds of demolition", and "a list of documents that the noticee is required to furnish along with his reply". It adds: "The notice should also specify the date on which the personal hearing is fixed and the designated authority before whom the hearing will take place".
- Record. A(iv) says that once the notice is served, intimation "shall be sent to the office of Collector/District Magistrate of the district digitally by email". It also asks for "an auto generated reply acknowledging receipt of the mail". A(vi) says every municipal or local authority "shall assign a designated digital portal, within 3 months from today", showing the notice, the reply and the order.
- B. Hearing. B(i) says: "The designated authority shall give an opportunity of personal hearing to the person concerned." B(ii) says the minutes "shall also be recorded".
- C. Final order. After the hearing, the authority "shall pass a final order". C(ii) lists what it "shall contain". One item is "as to why the extreme step of demolition is the only option available and other options like compounding and demolishing only part of the property are not available."
- D. Time to appeal. D(i) is quoted in the next section. D(ii) says: "An opportunity should be given to the owner/occupier to remove the unauthorized construction or demolish the same within a period of 15 days".
- E. The demolition. E(i) says the demolition "shall be video-graphed", with a demolition report listing the police and civil staff who took part.
The directions use "show cause notice" without defining it. A Delhi law quoted below uses the words "showing cause why such order shall not be made".
How much time does a demolition notice give?
The directions name two separate 15-day periods. The first is in A(i), quoted above: the local law’s time or 15 days, "whichever is later". The directions do not explain the word "returnable".
The second comes after the final order. D(i) says:
We further direct that if the statute provides for an appellate opportunity and time for filing the same, or even if it does not so, the order will not be implemented for a period of 15 days from the date of receipt thereof.
D(ii) then says:
Only after the period of 15 days from the date of receipt of the notice has expired and the owner/occupier has not removed/demolished the unauthorized construction, and if the same is not stayed by any appellate authority or a court, the concerned authority shall take steps to demolish the same.
D(ii) speaks of "receipt of the notice", while D(i) speaks of receipt of the order. We quote both as printed and do not try to reconcile them. Our stay order guide explains what a court stay means.
Figures that are not directions. Paragraph 10 reproduces counsel’s suggestions, such as "Minimum 2 months" to reply and a response period of "no less than 45 days and no more than 60 days". Paragraph 11 reproduces the Solicitor General’s suggestions. One says that where a notice period is not provided "and the case does not fall within the exception noted in paras 2 and 3 below, a reasonable notice period of one week to 10 days may be read into the relevant statute". Another gives "48 hours – 72 hours" after a final order. These are suggestions recorded in the judgment. The directions in paragraph 91 do not contain them.
Which demolitions do the directions not cover?
Paragraph 91 begins:
At the outset, we clarify that these directions will not be applicable if there is an unauthorized structure in any public place such as road, street, footpath, abutting railway line or any river body or water bodies and also to cases where there is an order for demolition made by a Court of law.
The same carve-out appeared in the court’s order of 17 September 2024, as paragraph 6 records. The judgment says the directions "will not be applicable" to these cases. We read no sentence in it saying that such structures need no notice at all.
In paragraph 11, the Solicitor General suggested: "At best, the illegal encroachers on the said public land/public place, may be granted 48 hours to vacate such encroachment." That was a suggestion. It is not among the directions.
Some local laws allow removal of some things without notice. In Delhi, for example, section 322 of the Delhi Municipal Corporation Act, 1957 says:
The Commissioner may, without notice, cause to be removed—(a) any stall, chair, bench, box, ladder, bale or other thing whatsoever, placed, deposited, projected, attached or suspended in, upon, from or to any place in contravention of this Act
We read a copy dated 18 April 2022. Clause (b) covers articles "hawked or exposed for sale on any public street or in other public place in contravention of this Act". This is a Delhi law only.
Do state and city laws still matter?
Yes. Direction A(i) itself refers to "the time provided by the local municipal laws". Each state and city has its own Acts. We read parts of three.
Delhi. Section 343(1) of the Delhi Municipal Corporation Act, 1957 covers building work done "without or contrary to the sanction referred to in section 336", among other cases. The Commissioner "may" order its demolition "by the person at whose instance the erection or work has been commenced or is being carried on or has been completed". The period is:
within such period (not being less than five days and more than fifteen days from the date on which a copy of the order of demolition with a brief statement of the reasons therefor has been delivered to that person), as may be, specified in the order of demolition
Its first proviso says:
Provided that no order of demolition shall be made unless the person has been given by means of a notice served in such manner as the Commissioner may think fit, a reasonable opportunity of showing cause why such order shall not be made
Section 343(2) allows an appeal to the Appellate Tribunal. These rules are for Delhi only.
Jaipur. We read the Jaipur Development Authority (JDA) Act, 1982 only in an Indian Kanoon copy dated 7 April 2007. We did not confirm the current text. In that copy, section 32(1) applies where development "has been carried out as indicated in sub-section (1) of section 31". It goes on:
the Authority may, subject to the provisions of this sections, within three years of such development, serve on the owner a notice requiring him, within such period, being not exceeding one month, as may be specified therein after the service of the not ice, to take such steps as may be specified in the notice
The copy prints "sections" and "not ice" that way. Section 32(2) says the notice may require "the demolition or alteration of any building or works". For temporary development, section 34(1) says:
the Authority may, by an order in writing direct that person to remove any structure or work erected, or discontinue the use of land made, unauthorisedly as aforesaid, within fifteen days of the receipt of the order; and if thereafter, the person does not comply with the order within the said period, the Authority or any officer authorised by it in this behalf may get such work summarily removed or get such use summarily discontinued without any notice as directed in the order; and any development unauthorisedly made again shall similarly be summarily removed or discontinued without making any order as aforesaid
Section 83(8) begins "Except as otherwise provided". Clause (a) says:
any person aggrieved by an order or notice of the Authority may file an appeal in the Tribunal within thirty days of the communication of such order or notice to him
Because the current text is not confirmed, we give no time limit as Jaipur’s law today.
Udaipur. A 2026 Rajasthan High Court ruling, below, reproduces section 32(1) of the Udaipur Act of 2023, as the ruling calls it ("the Act of 2023"). In that Act, the notice may be served "within ten years of such development". It gives a period "being not exceeding one month". We read this only as the ruling reproduces it.
Forest land. Section 4(5) of the Forest Rights Act, 2006 says:
Save as otherwise provided, no member of a forest dwelling Scheduled Tribe or other traditional forest dweller shall be evicted or removed from forest land under his occupation till the recognition and verification procedure is complete.
We read it in an Indian Kanoon copy dated 29 December 2006. Our forest clearance guide explains how this fits with forest clearance.
What happens if the directions are not followed?
Paragraph 93 says:
It will also be informed that violation of any of the directions would lead to initiation of contempt proceedings in addition to the prosecution.
Paragraph 94 says:
The officials should also be informed that if the demolition is found to be in violation of the orders of this Court, the officer/officers concerned will be held responsible for restitution of the demolished property at his/their personal cost in addition to payment of damages.
LawBeat reported on 16 July 2026 that the Supreme Court refused to entertain contempt petitions alleging breaches of the 2024 judgment. It said a bench led by Chief Justice Surya Kant said such grievances should be raised before the High Courts. LawBeat quoted the order: "We deem it appropriate to transfer the records of these proceedings to the concerned High Courts". We did not read the order itself.
What have courts said in 2026?
Rajasthan High Court, Udaipur shop sealing. On 9 October 2026, Justice Nupur Bhati of the Rajasthan High Court at Jodhpur ruled in 2026:RJ-JD:49669. The case was about sealing a shop under the Udaipur Act, not a demolition. Paragraph 56 says "the respondents have failed to satisfactorily establish compliance with the statutory requirements governing the notice and service" under section 32, "insofar as the petitioner is concerned". Paragraph 40 says:
The statutory notice is, therefore, not an empty formality; it serves the substantive purpose of informing the person concerned of the proposed action and enabling that person to avail the remedies contemplated by the Act.
Paragraph 57 says the sealing action "is hereby set aside insofar as it affects the petitioner and is founded upon the impugned proceedings." That was the holding in that case. Paragraph 55 says two Supreme Court judgments relied on by the respondents, including the 2024 one, "have no applicability to the instant case". Paragraph 48 left the petitioner’s objection on the ten-year limit open.
Supreme Court, August 2026. Deccan Herald reported on 12 August 2026 that the Supreme Court declined to entertain a public interest litigation (PIL). The PIL sought a uniform policy on regularising and demolishing long-standing unauthorised constructions. Deccan Herald quoted the bench: "It would be difficult and may not be prudent for this court to lay down a uniform policy framework to be applied across various states". Deccan Herald said the court asked states and Union territories "to consider a representation seeking a uniform policy".
What could we not confirm?
- The current text of the Jaipur Development Authority Act, 1982. We read only a copy dated 7 April 2007.
- The Supreme Court’s order of 16 July 2026. We read it only as LawBeat quotes it.
- Whether each state has set up the digital portal named in direction A(vi).
- The Udaipur Act of 2023 itself. We read section 32(1) only as the 2026 ruling reproduces it.
- Later Supreme Court orders in the 2024 case, other than as LawBeat reports one.
Examples from our reports
We link one live report. Its line keeps the page’s own words and outlets, as on its update date. See also: our land survey guide, our master plan guide and our land acquisition guide.
- New Sanganer Road demolition protests, Jaipur: updated 11 October 2026. The page says: "On Rajasthan High Court directions, the Jaipur Development Authority (JDA) began a court-ordered drive on 5 October to remove structures it has marked as encroachments on New Sanganer Road, between Sodala and Gurjar Ki Thadi." It says "JDA served notices on 27 September, ETV Bharat reports, quoting the traders’ body". It adds that Urban Acres says owners were given six days, to 3 October. Citing a JDA official via ETV Bharat, the page says "objections to the notices would be examined". Urban Acres also says the traders’ association chair and three others "had stays from a JDA tribunal against the 27 September notices". The page could not confirm whether the drive is paused. Its outcome is not in our reports. We do not say how the 2024 directions apply to it.
Frequently asked questions
Did the Supreme Court ban bulldozer demolitions?
No. The 2024 judgment sets steps before a demolition: a notice, a hearing, a final order and time to appeal. Paragraph 91 says the directions "will not be applicable" to unauthorised structures in public places and to court-ordered demolitions.
How many days' notice must be given before a demolition?
Under direction A(i), the notice runs for the local law’s time or 15 days, "whichever is later". Direction D(i) adds that the final order "will not be implemented for a period of 15 days from the date of receipt thereof". Local laws can set other periods.
Do the directions cover a shop or a structure on a road or footpath?
The directions do not single out shops; paragraph 1 speaks of "residential and commercial properties". Paragraph 91 excludes "an unauthorized structure in any public place such as road, street, footpath" and some other places. The judgment does not say what notice applies in those cases.
Does a court-ordered demolition need the same notice?
The 2024 directions do not apply "to cases where there is an order for demolition made by a Court of law", paragraph 91 says. The judgment does not say what notice applies then. We read no single national rule on this.
What if the directions are not followed?
Paragraph 93 says a violation "would lead to initiation of contempt proceedings in addition to the prosecution". In July 2026, LawBeat reported, the Supreme Court transferred the records of contempt petitions to the High Courts. This is general information, not legal advice.
This guide is general information, not legal advice. It draws on a 2024 Supreme Court judgment, parts of three Acts, a 2026 High Court ruling, two news reports and one live report. Each source is dated where it gives a date, and credited. It takes no side on any government, party, community or group.
Last checked 27 October 2026.
Sources
Accessed 27 October 2026. The tag shows how much of each source we read: in full, only in part (for example a paywalled or cut-off article), or not at all.
- Supreme Court of India, In Re: Directions in the matter of demolition of structures, Writ Petition (Civil) No. 295 of 2022, 2024 INSC 866, 13 November 2024. Read in full Read in full by the law and accuracy researchers. The writer re-read paragraphs 1-13 (with the counsel and Solicitor General tables), 71-72, 83-84 and 88-99 in the court’s PDF.
- The Jaipur Development Authority Act, 1982 (Indian Kanoon copy, version of 7 April 2007), 7 April 2007. Partly read Sections 32, 34(1) and 83(8) read by the writer. The current text was not confirmed.
- The Delhi Municipal Corporation Act, 1957 (Indian Kanoon copy, version of 18 April 2022), 18 April 2022. Partly read Sections 321, 322 and 343 read by the writer. Delhi only.
- The Scheduled Tribes and Other Traditional Forest Dwellers (Recognition of Forest Rights) Act, 2006 (Indian Kanoon copy). Partly read Section 4(5) read by the writer (copy dated 29 December 2006).
- Rajasthan High Court at Jodhpur, S.B. Civil Writ Petition No. 21162/2026, 2026:RJ-JD:49669 (Udaipur shop sealing) (Indian Kanoon copy), 9 October 2026. Read in full Read by the writer. Cited by neutral citation; the title names a private person.
- Deccan Herald, "Supreme Court asks states to consider framing policy on demolition, regularisation of illegal constructions", 12 August 2026. Read in full Read by the writer from the page’s article text.
- LawBeat, "Supreme Court Rejects Pleas Alleging Violation Of Its Guidelines On Bulldozer Action", 16 July 2026. Read in full Read by the writer. Only the order quote and the outcome are used.
- All India Protest, New Sanganer Road demolition protests, Jaipur (our live report), updated 11 October 2026. Read in full Used for the example line only.
- ETV Bharat and Urban Acres. Not read Named only as our live report credits them; not opened for this guide.
- The Supreme Court’s order of 16 July 2026; the Udaipur Act of 2023; the current Jaipur Development Authority Act; later orders in the 2024 case. Not read Not opened.
Spotted an error, or a source we missed? Email a correction with the source that shows it. See how we handle corrections. Back to top