River interlinking in India: what it is and who opposes it
What it is The 1980 plan Supreme Court Ken-Betwa Where links stand Why people oppose Our reports FAQ Sources
Short answer
River interlinking means moving water "from surplus basins to deficit basins and regions", a July 2025 government reply says. It counts 30 links under the National Perspective Plan, which NWDA dates to 1980. Ken-Betwa is the only one whose implementation has started, it says. Ken-Betwa protesters alleged violations on land acquisition, rehabilitation and "environmental safeguards", PTI reported in 2026.
This guide is general information, not legal advice. It describes what a Supreme Court judgment, government releases and National Water Development Agency (NWDA) pages say. It takes no side and tells no one what to do. We describe the texts as we read them on 18 October 2026.
River-linking projects often make news when villagers protest. This guide explains what a river link is, who plans it, and where the plan stands. Each line names its source and date.
What is river interlinking?
On 28 July 2025 the Minister of State for Jal Shakti gave a written reply in the Rajya Sabha. PIB published it. It opens:
The Government of India formulated the National Perspective Plan (NPP) for the Inter-Linking of Rivers (ILR) programme to facilitate the transfer of water from surplus basins to deficit basins and regions.
Ken-Betwa is the first link under implementation, NWDA says. Its note says the project "envisages diversion of surplus water of Ken basin to water deficit Betwa basin."
What "surplus" means. NWDA’s overview of the 1980 plan says "only surplus flood water after meeting all in-basin requirement in foreseeable future has been planned for transfer to water deficit areas." We read no official page that defines a surplus or deficit basin more exactly. At Bedti in Karnataka, an activist quoted by Deccan Herald disputes the surplus figures, our report says (see below).
The Hindi terms. The Hindi version of the same PIB release is headed nadiyon ko aapas mein jodne wali pariyojanaen. The English release is headed "RIVER INTERLINKING PROJECTS". It calls the NPP the Rashtriya Pariprekshya Yojana (National Perspective Plan). It calls a DPR a vistrit pariyojana report (detailed project report).
What is the National Perspective Plan?
NWDA’s overview page says the then Ministry of Irrigation and the Central Water Commission:
formulated a National Perspective Plan (NPP) for Water Resources Development in 1980, envisaging inter basin transfer of water from surplus basins to deficit ones with a view to minimize the regional imbalances and optimally utilize the available water resources.
The plan "comprises of two components viz. Himalayan Rivers Development and Peninsular Rivers Development", the overview says.
How many links? The July 2025 reply says: "A total of 30 ILR projects have been identified, encompassing two major components: the Himalayan Component with 14 link projects and the Peninsular Component with 16 link projects." The reply gives no year for when the 30 were identified. The NWDA overview we read gives no count.
The pages we read call the NPP a plan. None of them names an Act behind it.
Who plans a link. NWDA "was set up in July 1982 as Autonomous Society under the societies registration act 1860", its overview says. On 7 October 2016, it adds, "the functions of NWDA were further modified to undertake implementation of ILR projects", among other tasks.
The July 2025 reply says NWDA "has been entrusted with the responsibility of implementing the ILR projects under the NPP framework". It names three kinds of report: Pre-Feasibility Reports (PFRs), Feasibility Reports (FRs) and Detailed Project Reports (DPRs). We read no official definition of each.
Who agrees and pays, for Ken-Betwa. NWDA’s note says "A tripartite Memorandum of Agreement (MoA) was signed among the party States of UP and MP with Union Government on 22.03.2021 for implementation of the project." PIB says the Union Cabinet "has approved the funding and implementation" of the project, in a release of 8 December 2021. NWDA’s two files print different dates: 07.12.2021 in its Ken-Betwa note and 08.12.2021 in its clearance table. Land acquisition and resettlement are to be carried out by the two states, the 2025 reply says.
Did the Supreme Court order river links?
On 27 February 2012 a three-judge bench of the Supreme Court decided two petitions on networking rivers. The judgment’s title reads "IN RE : NETWORKING OF RIVERS" (Writ Petition (Civil) No. 512 of 2002, with No. 668 of 2002).
Justice Swatanter Kumar wrote the judgment. Chief Justice S.H. Kapadia and Justice A.K. Patnaik were on the bench. In short, the court directed the Union to set up a committee. It left planning and environmental issues to the governments, in its own words.
What the court said it could not do (para 62).
The Court can hardly take unto itself tasks of making of a policy decision or planning for the country or determining economic factors or other crucial aspects like need for acquisition and construction of river linking channels under that program. The Court is not equipped to take such expert decisions and they essentially should be left for the Central Government and the concerned State.
The same paragraph says: "The planning, acquisition, financing, pricing, civil construction, environmental issues involved are policy decisions affecting the legislative competence and would squarely fall in the domain of the Government of States and Centre." It ends: "We certainly should not be understood to even imply that the proposed projects of inter-linking of rivers should not be completed."
What it recommended (para 63). "We would recommend, with all the judicial authority at our command, that these projects are in the national interest, as is the unanimous view of all experts, most State Governments and particularly, the Central Government." This is a recommendation, not a direction.
What it directed (para 64). In para 64(I), the court directed the Union and the Ministry of Water Resources "to forthwith constitute a Committee". The committee was to be called the Special Committee for Inter-linking of Rivers. Its members include the Minister for Water Resources, secretaries, the Central Water Commission chairman, four experts, state ministers and "Two social activists to be nominated by each of the concerned Ministries."
On Ken-Betwa, para 64(VIII) says in full:
We are informed that large sums have been spent on preparation of initial and detailed project reports of the project `Ken-Betwa Project’. The DPR is now ready. The States of Madhya Pradesh and Uttar Pradesh and also the Central Government had already given their approval and consent. The clarifications sought will be discussed by the Committee. We would direct the Committee to take up this project for implementation at the first instance itself.
So the court directed the committee to take up Ken-Betwa first. It recorded that both states and the Centre had consented. We searched the judgment for "clearance" and "rehabilitat". "Clearance" appears only where it recounts affidavits and status reports (paras 20 and 28). "Rehabilitat" appears only inside a quoted study (para 44). We found no line that grants a clearance or decides rehabilitation.
Para 64(V) says: "The Committee shall submit a bi-annual report to the Cabinet of the Government of India placing before it the status-cum-progress report as well as all the decisions required to be taken in relation to all matters communicated therewith." It adds: "The Cabinet shall take all final and appropriate decisions, in the interest of the countries as expeditiously as possible and preferably within thirty days from the date the matters are first placed before it for consideration." ("countries" is as printed.)
In para 66 the court told the Central and State Governments concerned to comply with its directions "effectively and expeditiously and without default." These directions were made in that case.
The committee now. NWDA has a page for the "Special Committee for ILR". It lists a "Notification dated 23-09-2014" and meetings up to the 25th, held on 15.07.2026. The notification is a scanned file we could not read. So we do not say how it relates to the 2012 judgment.
What is the Ken-Betwa link?
PIB’s FAQ on the project (21 August 2026) says it involves:
transfer of water from the Ken to the Betwa River through construction of the 96.7 m high Daudhan Dam on the Ken River in Panna and Chhatarpur districts of Madhya Pradesh, about 40 km from Khajuraho.
The FAQ adds: "A 216.465 km-long Ken–Betwa Link Canal will take off near the Daudhan Dam and merge into Barua Sagar near Jhansi."
Approval and cost. On 8 December 2021, PIB said "The Union Cabinet chaired by the Prime Minister Shri Narendra Modi, today has approved the funding and implementation of Ken-Betwa inter-linking of rivers project." The cost "has been assessed at Rs.44,605 crore at 2020-21 price levels". Central support was Rs 39,317 crore, the release says.
Who runs it. The 2021 release names a "Special Purpose Vehicle (SPV) called Ken-Betwa Link Project Authority (KBLPA)". NWDA’s note says a Gazette notification of 11 February 2022 set up "a Steering Committee and Ken-Betwa Link Project Authority (KBLPA) for the implementation of KBLP jointly by Government of India and State Governments of MP and UP".
What the government says it will do. The 2021 release says the project "will provide an annual irrigation of 10.62 lakh ha, drinking water supply to a population of about 62 lakhs and also generate 103 MW of hydropower and 27 MW solar power." Its summary points give the area as "10.62 lakh hectares".
On drought, the 2026 FAQ says: "It would not be appropriate to claim that the project will completely eliminate drought."
Clearances. The 2026 FAQ lists "Environmental Clearance (2017), Wildlife Clearance (2016), Clearance from the Ministry of Tribal Affairs (2017), and Forest Clearance (2023)". NWDA’s undated clearance table says environmental clearance "has been granted by MoEF&CC on 25.08.2017 with certain conditions". MoEF&CC is the Ministry of Environment, Forest and Climate Change.
The same table has a row on review by the Central Empowered Committee "constituted by Hon’ble Supreme Court of India". It says: "It is being pursued from time-to-time." We did not read that committee’s report.
People affected. The July 2025 reply says:
As per records available at the time of issuance of Section-11 under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (RFCTLARR Act, 2013), the project involves 7,193 Project Affected Families (PAFs).
The 2026 FAQ says "A Project Affected Family means a family whose land, house, property, forest rights, or main source of livelihood is affected due to land acquisition for the project." The Hindi release calls these pariyojana prabhavit parivar (project affected families).
The FAQ also says "22 villages are affected — 8 in Panna district and 14 in Chhatarpur district", in Madhya Pradesh. It says: "Across the project, awards worth about ₹629.87 crore have been passed for 5,039 affected families, and about ₹604.745 crore (around 96%) has already been paid out." These figures come from different dates and counts. We do not compare them.
On the 2021 agreement, the 2025 reply says: "Rehabilitation & Resettlement of project affected families and land acquisition for the projects within their territorial jurisdiction would be carried out by respective State Governments viz; Madhya Pradesh and Uttar Pradesh as per the RFCTLARR Act, 2013 or as per the respective State Policies."
The 2026 FAQ describes Madhya Pradesh’s 2023 package: "Under the Special Package, compensation for acquired land is paid at either the rate determined by the Act or ₹12.50 lakh per hectare, whichever is higher, with compensation for houses, trees, wells, tube wells and other immovable assets similarly determined under the Act." For what the 2013 land law says about rehabilitation before submergence, see our guide to dam-displacement protests and oustees.
Where are the links now?
The July 2025 reply says: "As of July 2025, Pre-Feasibility Reports (PFRs) have been completed for all 30 projects, Feasibility Reports (FRs) for 26 projects, and Detailed Project Reports (DPRs) for 11 link projects."
It calls Ken-Betwa "the first interlinking initiative under the National Perspective Plan (NPP) to have entered the implementation stage." For the other links, it says, budget matters "will be taken up once these projects advance to the implementation phase."
The reply also says: "As KBLP is the only project of NPP, for which implementation has been started, so information sought as related to KBLP is given below:" Its table adds that the Godavari (Polavaram)-Krishna (Vijayawada) link "has been taken up by Government of Andhra Pradesh." The same table lists that link as "FR completed". It does not say what stage the state’s work has reached.
| Source | Date | What it says |
|---|---|---|
| Rajya Sabha reply (PIB) | 28 July 2025 | "The Ken-Betwa Link Project (KBLP) is the first interlinking initiative under the National Perspective Plan (NPP) to have entered the implementation stage." |
| NWDA Ken-Betwa note | Undated; figures up to 31 July 2025 | "KBLP is the first Inter-linking of Rivers (ILR) project which is under implementation." "The project is planned to be completed by March, 2030." |
| PIB FAQ on Ken-Betwa | 21 August 2026 | "The dam is under construction, while work on the canal is yet to begin." "The Project is scheduled for completion in 2030." |
Each cell quotes the source named in its row. Planned dates are each source’s plan, not our forecast.
Other links. The 2025 reply’s table gives each link’s stage. Two more of its notes:
- Netravati-Hemavati: "Further studies are not taken up since after implementation of Yettinahole project by Government of Karnataka, no surplus water is available in Netravati basin for diversion through this link."
- Bedti-Varda (spelt Bedti-Varada in our report): listed as "DPR completed", with the note "DPR was prepared directly after preparation of its PFR, no FR was prepared."
Our Bedti-Aghanashini report cites Deccan Herald on a December 2025 step. Karnataka’s then Deputy Chief Minister said the state had given in-principle approval for NWDA to prepare the Bedti-Varada DPR. We did not check how this fits the 2025 table.
Why do people oppose river-link projects?
The reasons below come from the 2012 judgment’s record, official releases and news reports. Each line is one source’s account, not our view.
- States’ rights over their water. The 2012 judgment records state affidavits (para 19). It says Assam, Sikkim and Kerala "had raised their protests on the grounds that they should have exclusive right to use their water resources and that such transfer should not affect any rights of these States." It adds that Kerala "entirely objected to long distance, inter-basin, water transfer."
- Doubts about the water itself. The judgment says the Union and some states raised concerns (para 22). These included "questioning the reliability of water supply from distant sources, distribution of water given the existing tribunal awards and the continued availability of existing water surpluses."
- Land under water. For the Par-Tapi-Narmada and Damanganga-Pinjal links, the judgment says "residents have shown concern about the extent of land to be submerged on the construction of the proposed dam" (para 29). Gujarat and Maharashtra then set up committees "to take up the matters with the panchayats and to commence the projects", it says.
- The cost of resettlement. The judgment quotes a 2008 economic study by the National Council for Applied Economic Research. The study says: "One shortcoming of the above analysis is that it has not considered the issue of cost of resettlement of displaced people due to ILR Project."
- Forests and wildlife. The July 2025 reply says about 17,101 trees were identified for felling for the Daudhan Dam and allied infrastructure. "Of these, 12,404 trees have been felled within the Panna Tiger Reserve Forest." The 2026 FAQ says the project "has significant environmental and wildlife considerations because of its proximity and relationship with the Panna landscape."
- Compensation and rehabilitation. PTI, carried by ThePrint (19 July 2026), reported a protest in Chhatarpur district "against the Ken-Betwa Link and other development projects". It said protesters were "alleging violations related to land acquisition, rehabilitation, environmental safeguards and project implementation." In the same report, "The administration has rejected the allegations and maintained that the project is being executed in accordance with the law."
- Livelihoods and the "surplus" claim. In Karnataka, our Bedti-Aghanashini report cites Deccan Herald on concern for farmers, fishers and forest-dependent communities. An activist quoted by Deccan Herald disputes the figures for surplus water, our page says.
What the government says. On 15 August 2026, Akashvani News reported a Ministry of Jal Shakti statement. It said the allegations of families not being compensated or rehabilitated were "incorrect and misleading".
The report says "the Ministry said that most eligible families have received full compensation and rehabilitation benefits, and only procedural formalities remain in a few cases." The 2026 FAQ speaks of "implementing mitigation and R&R measures for unavoidable impacts." R&R means rehabilitation and resettlement, as the FAQ writes it out.
On the states’ side, the 2012 judgment said their reservations need a framework first. See the FAQ below. For how river disputes between states are decided, see our guide to interstate river water disputes.
Examples from our reports
This is our own report. The line uses the live page’s words and the outlets it names, as of the page’s last update. We link one live report here. See also: our guide to dam-displacement protests and oustees and our guide to interstate river water disputes.
- Bedti-Aghanashini river-linking protest in Karnataka: the page (updated 11 October 2026) says people rallied at Freedom Park, Bengaluru, on 10 October 2026 "against two proposed river links, Bedti-Varada and Aghanashini-Vedavati." They want both projects scrapped and the Bedti-Varada DPR process stopped, it says, citing Deccan Herald, The Hindu, Kannada Prabha and Vishwavani. On approval, it says: "The sources we read report approval only for preparing a project report."
Frequently asked questions
How many river links are planned in India?
Thirty, in the Rajya Sabha reply of 28 July 2025: 14 Himalayan and 16 Peninsular links. As of July 2025, it says, PFRs were complete for all 30, FRs for 26 and DPRs for 11.
Which is India's first river-linking project?
Ken-Betwa. The July 2025 reply calls it "the first interlinking initiative under the National Perspective Plan (NPP) to have entered the implementation stage."
Is the Ken-Betwa project complete?
Not as of 21 August 2026. PIB’s FAQ says "The dam is under construction, while work on the canal is yet to begin." It says the project "is scheduled for completion in 2030."
Did the Supreme Court order the government to link rivers?
In 2012 it directed the Union to set up a Special Committee for Inter-linking of Rivers. It directed that committee to take up Ken-Betwa "for implementation at the first instance itself". Para 62 left planning and environmental issues to the governments.
Do states have to agree to a river link?
The 2012 judgment said states’ reservations "squarely fall within the domain of general consensus and thus, require a framework to be formulated by the competent Government or the Legislature, as the case may be, prior to its execution" (para 50). For Ken-Betwa, both states signed an agreement with the Union in 2021. This is general information, not legal advice.
This guide is general information, not legal advice. It describes what a 2012 Supreme Court judgment, PIB releases, NWDA pages and two news reports say. It does not tell anyone what to do, and it does not rate any government, authority or group. Figures and stages change; the official text prevails over any copy.
Last checked 18 October 2026.
Sources
Accessed 18 October 2026. The tag shows how much of each source we read: in full, only in part (for example a paywalled or cut-off article), or not at all.
- Supreme Court of India, "IN RE : NETWORKING OF RIVERS", Writ Petition (Civil) No. 512 of 2002 with No. 668 of 2002, judgment (Indian Kanoon), 27 February 2012. Read in full Read by the writer.
- PIB, Ministry of Jal Shakti, "RIVER INTERLINKING PROJECTS" (Rajya Sabha written reply), 28 July 2025. Read in full English release and its table, read by the writer.
- PIB, Hindi release of the same reply, 28 July 2025. Partly read Text paragraphs and the start of the table.
- PIB, "Cabinet approves Ken-Betwa Interlinking of Rivers Project", 8 December 2021. Read in full
- PIB explainer, "Ken-Betwa Link Project", Frequently Asked Questions (FAQs), 21 August 2026. Read in full
- National Water Development Agency (NWDA), "Overview", last updated 10 August 2026. Read in full
- NWDA, "Ken-Betwa Link Project (KBLP)" note, undated; figures up to 31 July 2025. Read in full
- NWDA, "Status of various clearances" (Ken-Betwa Link Project), undated. Read in full
- NWDA, "Special Committee for ILR" page, accessed 18 October 2026. Read in full The list page only. The 23 September 2014 notification is a scan we could not read.
- ThePrint (PTI), "Police clear out tribals protesting against Ken-Betwa link project in MP’s Chhatarpur", 19 July 2026. Read in full
- Akashvani News, "Jal Shakti Ministry rejects allegations of inadequate compensation under Ken-Betwa Project", 15 August 2026. Read in full
- All India Protest, Bedti-Aghanashini river-linking protest in Karnataka (our live report; it names Deccan Herald, The Hindu, Kannada Prabha and Vishwavani, among others), updated 11 October 2026. Read in full
- The Central Empowered Committee’s report on Ken-Betwa; the 2017 National Green Tribunal appeal against the Ken-Betwa clearance and any Supreme Court orders on these; the Special Committee notification of 2014; the full 2008 NCAER study (quoted only as the 2012 judgment quotes it); the 2021 agreement and the 2022 Gazette notification; Madhya Pradesh’s 2023 package order; the Union Cabinet’s own papers; search-result pages. Not read Nothing on this page rests on them.