Can residents object to a metro, flyover or elevated corridor route in India?

How routes are decided Metro objections NH Act Flyovers 2017 policy Courts Not confirmed Our reports FAQ Sources

Short answer

Sometimes. Where the 1978 metro Act or the National Highways Act is used to take land, a person interested in it may object. The window is 21 days from the notice each Act names, and the authority’s order "shall be final". We found no single flyover law. The 2017 metro policy copy we read has no public objection step.

This guide is general information, not legal advice. It describes what two Acts, a central policy, court rulings and news reports say. It does not tell anyone what to do. Which law applies depends on the project and the place.

Each point below is credited to the law, court or outlet that stated it. Rulings whose titles name private parties are cited by court, year and citation only. Where a point is unconfirmed, we say so.

Key words, from the texts we read

  • Alignment: the 1978 metro Act defines a "metro alignment". It "means such alignment of the metro railway as is specified in the Schedule under that city and includes the metro railway" (s. 2(1)(h)). We could not read a dictionary entry for the plain word. The National Highways Act does not use the word "alignment" in the copy we read.
  • Notification: in both Acts, the Central Government first declares that it intends to take land. It does so "by notification in the Official Gazette" (metro Act s. 7(1); National Highways Act s. 3A(1)). Each Act lets it do this only once it is satisfied the land is needed for a public purpose.
  • Objection: in both Acts, an objection "shall be made to the competent authority in writing and shall set out the grounds thereof" (metro Act s. 9(2); National Highways Act s. 3C(2)).
  • Competent authority: the officer who hears objections. Under the National Highways Act, it is "any person or authority authorised by the Central Government, by notification in the Official Gazette, to perform the functions of the competent authority for such area as may be specified in the notification" (s. 3(a)). Under the metro Act, the Centre "shall" appoint one for every metro railway (s. 16(1)). That person must be "holding, or has held, a judicial office, not lower in rank than that of a subordinate Judge" (s. 16(2)).
  • Public hearing: neither Act uses these words in the copies we read. Each gives an objector "an opportunity of being heard".
  • Person interested: neither Act defines it in its definitions section. We do not explain it further.

How are metro and highway routes decided?

We found no single text that sets one process for every metro, highway and flyover. The texts we read show these steps.

Metro: the 2017 policy. The Metro Rail Policy 2017 says proposals for central assistance "will have to be mooted by the State Government". It calls a Comprehensive Mobility Plan "a mandatory prerequisite for planning metro rail in any city". It says the project report "will be the key document for assessing the feasibility of a metro project and the issue of central assistance".

Metro: the 1978 Act. Under section 32(1)(a), the Central Government may, by notification in the Official Gazette, "add to the Schedule the metro alignment" for a place where the Act applies. Section 32(2) says each such notification "shall, as soon as may be after it is issued, be laid before each House of Parliament".

One example, as a court recorded it. In a 2023 case on Mumbai Metro Line 4, the Bombay High Court set out the steps for that line. It said a project report was approved by the Mumbai Metropolitan Region Development Authority (MMRDA) in June 2016. The ruling gives the date as both 30 June and 3 June. MMRDA put the alignment on its website in November 2016. It gave a newspaper notice of a "public consultation", held on 16 January 2017. The Centre then added the alignment to the Act’s Schedule by a notification of 23 March 2017. That was one project, in that case.

Highways. The National Highways Act says the Central Government "may, by notification in the Official Gazette, declare any other highway to be a national highway" (s. 2(2)). In a 2011 ruling, the Supreme Court described how NHAI plans. It said: "NHAI prepares and implements projects relating to development and maintenance of National Highways after thorough study by experts in different fields." It added: "Detailed project reports are prepared keeping in view the relative factors including intensity of heavy vehicular traffic and larger public interest."

A city example. For the Thane Integral Ring Metro, Newsband reported on 24 September 2026 that "Mahametro officials stated that the route was approved by the Thane Municipal Corporation general body in 2018."

Can residents object to a metro route?

The 1978 metro Act has an objection step. It works only where the Act applies, and only when its land chapter is used.

Where the Act applies. Section 1(3) says it "applies in the first instance to the metropolitan city of Calcutta". The Central Government "may, by notification in the Official Gazette, declare that this Act shall also apply to the National Capital Region, such other metropolitan city and metropolitan area, after consultation with the State Government, and with effect from such date as may be specified in that notification and thereupon the provisions of this Act shall apply to the National Capital Region, such metropolitan city or metropolitan area accordingly". So, by its text, the Act reaches places other than Calcutta only by notification. The 2023 Bombay High Court ruling records one such step: "By Notification dated 16th October 2009, the Central Government declared that the provisions of Metro Act 1978 would apply to the city of Mumbai." We did not read the notifications themselves or any official list of places.

Who may object, and to what. Section 9(1) says: "Any person interested in the land, building, street, road or passage may, within twenty-one days from the date of publication under sub-section (3) of section 7 of the substance of the notification under sub-section (1) of that section object to the construction of the metro railway or any other work connected therewith upon or under the land, building, street, road or passage, as the case may be."

When the 21 days start. They run from the publication of the notification’s "substance". Section 7(3) says this is published "in such places and in such manner as may be prescribed". We did not read the rules that set this. If it is published on different dates in different places, "the last of such dates shall be deemed to be the date on which substance of the notification has been published" (Explanation to s. 9(1)).

How it is heard. The objector is heard "either in person or by an agent or by a legal practitioner" (s. 9(2)). The competent authority "may, after hearing all such objections and after making such further enquiry, if any, as the competent authority thinks necessary, by order, either allow or disallow the objections".

Is the order final? Section 9(3) says: "Any order made by the competent authority under sub-section (2) shall be final." Section 9 does not mention an appeal or a review. If no objection is made, or it is disallowed, the Centre "shall declare, by notification in the Official Gazette" that the land should be acquired (s. 10(1)). Section 10(4) says that declaration "shall not be called in question in any Court or by any other authority."

When the land chapter is not used. Section 9 sits in Chapter III of the Act, headed "Acquisition". In the 2023 Mumbai case, the court records acquisition notifications issued under section 126 of the Maharashtra Regional and Town Planning Act, 1966. It said: "In the present case petitioners have not placed on record any material to show that the provisions of Chapter III of Metro Act 1978 were invoked, in any manner, by MMRDA for land acquisition." The court’s holding is set out under "What have courts said?" below.

Changing a route. Section 32(1)(b) lets the Centre "alter any metro alignment specified in the Schedule if it is of opinion that such alteration is necessary for the construction and maintenance of the metro railway to which such alignment relates." The text of section 32 contains no objection step.

Suits and injunctions. Section 39 says: "No suit or application for injunction shall lie in any Court against the Central Government or the metro railway administration or any officer or other employee of that Government or the metro railway or any person working for or on behalf of the metro railway administration, in respect of any work done or purported to have been done or intended to be done by it or the said administration or such officer or other employee or such person in connection with the construction of any metro railway or any other work connected therewith." We read no ruling on how section 39 applies to petitions in a High Court.

For the officials’ power to enter land and survey it under the same Act, see our guide to survey entry on land.

What does the NH Act say about objections?

The National Highways Act, 1956 "extends to the whole of India" (s. 1(2)). Its objection step is in section 3C.

  • The notice. The Centre declares its intention to acquire land "by notification in the Official Gazette" (s. 3A(1)). The competent authority then has the substance published "in two local newspapers, one of which will be in a vernacular language" (s. 3A(3)).
  • The objection. Section 3C(1) says: "Any person interested in the land may, within twenty-one days from the date of publication of the notification under sub-section (1) of section 3A, object to the use of the land for the purpose or purposes mentioned in that sub-section." By its text, the 21 days run from the Gazette notification.
  • The hearing. The objector is heard "either in person or by a legal practitioner" (s. 3C(2)). The authority may then "either allow or disallow the objections".
  • Final. "Any order made by the competent authority under sub-section (2) shall be final" (s. 3C(3)). The Centre’s later declaration "shall not be called in question in any court or by any other authority" (s. 3D(4)).
  • No word "alignment". The Act does not use the word alignment in the copy we read. The objection is to "the use of the land".

In the 2011 Supreme Court case on a highway widening, some owners raised the route itself. The court recorded: "Some others claimed that they had constructed shops etc. and the same can be saved if alignment of the highway was slightly changed." It recorded that the competent authority, "After hearing the objectors", rejected the objections.

Are flyovers covered by a special law?

We found none. We searched the 1978 metro Act and the National Highways Act for the word "flyover"; neither uses it. We read no state, municipal or planning law on flyover routes. So we cannot say which law applies to any one flyover.

In the texts we read, what matters is the law used for the project’s land. In the 2011 Supreme Court case, NHAI’s reply, as the judgment quotes it, said land was "required for the construction of the flyovers and widening of the road". Those objections were made against a notification under section 3A of the National Highways Act, the judgment records.

A flyover or elevated road may also appear in a city’s land-use plan. For how such plans are opened for objections, see our guide to master plans and land-use objections. For whether these projects need environmental clearance, see our guide to environmental clearance for metros, highways and flyovers.

Does the 2017 metro policy allow public objections?

The copy we read. The ministry’s own links to the policy did not open for us. We read a copy posted by the National Capital Region Transport Corporation (NCRTC). The Pune Metro website carries the same file. The copy prints no date. PIB reported on 16 August 2017 that the Union Cabinet "today approved a new Metro Rail Policy".

No public objection step. In the copy we read, the policy has no public consultation, hearing or objection step. Its one use of "consultation" is about governments. It says the Government of India "on its own may take up, after due consultation with the concerned state government(s)", projects "which are necessary for a city or metropolitan region development".

Alternatives mean transport modes. The policy says: "A comparative analysis of alternate modes should be an essential requirement for the transit mode selection." It adds: "The alternative analysis report will have to be necessarily incorporated in the project report while seeking central assistance." PIB said the policy "mandates Alternate Analysis, requiring evaluation of other modes of mass transit like BRTS (Bus Rapid Transit System), Light Rail Transit, Tramways, Metro Rail and Regional Rail in terms of demand, capacity, cost and ease of implementation."

Tied to central money. Many of its requirements are written as conditions for central assistance. For example: "Private participation either for complete provisioning of metro rail or for some unbundled components will form an essential requirement for all metro rail project proposals seeking central financial assistance." Others are written more widely, such as the mobility plan for "any city". Under "Legal Cover", it says: "All the metro rail projects will have to be governed by the Central Metro Acts." It does not name those Acts. PIB reports the policy as approved by the Union Cabinet; it is not an Act. We read no text that makes it binding on states.

What have courts said?

Supreme Court, 2011, national highway widening, (2011) 12 SCC 69. Two judges heard this case, and Justice G.S. Singhvi wrote the judgment. It said: "The Courts are not at all equipped to decide upon the viability and feasibility of the particular project and whether the particular alignment would subserve the larger public interest. In such matters, the scope of judicial review is very limited. The Court can nullify the acquisition of land and, in rarest of rare cases, the particular project, if it is found to be ex-facie contrary to the mandate of law or tainted due to mala fides." In that case, it said "neither any violation of mandate of the 1956 Act has been established nor the charge of malice in fact has been proved." It said "the order passed by the learned Single Judge dismissing the objections filed by the respondents is restored."

Bombay High Court, 2023, Mumbai Metro Line 4, 2023:BHC-OS:2159-DB. A two-judge bench held: "We therefore hold that for the purpose of acquisition of lands and buildings, a Metro Railway Administration is entitled to choose between provisions of Metro Act 1978 or any other enactment enabling land acquisition." It added: "In the present case MMRDA has resorted to the provisions of MRTP Act for land acquisition and we see no error on the part of MMRDA in doing so." The court dismissed the petitions. This was one High Court, in that case.

Himachal Pradesh High Court, October 2026, the Sanjauli tunnels (not a final ruling). Hindustan Times reported on 30 October 2026 that Justice Sandeep Sharma was hearing a petition filed by Sanjauli residents. HT quotes the order: "...this court restrains itself from passing an injunction order, but certainly hopes and trusts that till the next date of hearing, no further construction activity shall be carried out as far as construction of twin tunnels is concerned." HT reports the court asked NHAI why it gave up a surface highway. It also asked who would pay for the "₹ 600 crore spent for paying compensation for the land which was earlier proposed for construction of surface highway". HT gives 17 November 2026 as the next hearing date. We have not read the order itself.

What is not confirmed?

  • Where the 1978 Act applies today. Its text names Calcutta. A 2023 ruling records a 2009 notification for Mumbai. We read no other notification and no official list.
  • Which law a given project uses. None of the sources we read says which law is being used for land on the Thane or Sanjauli projects.
  • Who counts as a person interested. Neither Act defines it in its definitions section. We read no ruling on whether a neighbour whose land is not taken can object.
  • Section 39 and the courts. We read no ruling on how the section 39 bar sits with High Court petitions.
  • The rules and the Schedule. We did not read the rules under the 1978 Act, or its Schedule of alignments.
  • State laws. We read no state metro, planning or municipal law for this guide. Some may have their own objection steps.
  • The policy. We read a copy that is not on the ministry’s site. We did not check for later changes to it.

Examples from our reports

We link two of our live reports here. They are the only two live reports we link on this point. Both are older than this guide, so each line says the date of the page.

  • Thane Ring Metro residents' protests, Maharashtra (as of 23 October 2026): Maha Metro officials told Newsband the route was approved by the Thane Municipal Corporation general body in 2018. They said stations can be reconsidered but a change of alignment would need fresh approvals, our report says. On 4 October, marchers asked for the route to move to the proposed Foothill Road. They also asked for an underground route or another corridor (Free Press Journal, Loksatta and Mumbai Live, as cited in our report).
  • Sanjauli residents' protest against NHAI's twin tunnels, Shimla (as of 12 October 2026): After cracks appeared in buildings, the district administration directed NHAI on 19 September to stop tunnel work, Hindustan Times reported. Residents alleged the tunnel did not follow the earlier survey and raised the lack of a public hearing (Hindustan Times, PTI). Our page does not yet include the High Court hearing that Hindustan Times reported on 30 October 2026.

Frequently asked questions

My house is near a metro line but not taken. Can I object under the 1978 Act?

Section 9(1) gives the objection to "Any person interested in the land, building, street, road or passage" named in the notification. The Act does not define "person interested" in its definitions section. We read no ruling on neighbours whose land is not taken.

How long is the objection window?

Both Acts say "twenty-one days". Under the metro Act, the days run from the publication of the notification’s substance under section 7(3). Under the National Highways Act, they run "from the date of publication of the notification under sub-section (1) of section 3A". That is the Gazette notification.

Can a court stop a metro or highway route?

In 2011 the Supreme Court said courts are "not at all equipped to decide upon the viability and feasibility of the particular project and whether the particular alignment would subserve the larger public interest". It added that the Court "can nullify the acquisition of land and, in rarest of rare cases, the particular project, if it is found to be ex-facie contrary to the mandate of law or tainted due to mala fides." Section 39 of the metro Act bars any "suit or application for injunction" over metro construction work.

Can the government change an approved metro route?

Section 32(1)(b) of the metro Act lets the Centre "alter any metro alignment specified in the Schedule if it is of opinion that such alteration is necessary for the construction and maintenance of the metro railway to which such alignment relates." The notification goes before Parliament. For Thane, Newsband wrote: "While station locations can be reconsidered, any change in the metro alignment would require fresh approvals, including environmental clearances."

Is there a public hearing on a metro route?

Neither Act uses the words "public hearing" in the copies we read. Each gives an objector "an opportunity of being heard". The 2017 policy copy we read has no hearing step. In the 2023 Mumbai case, the court recorded a "public consultation" held by the agency for that line.

Does the 2017 Metro Rail Policy apply to every metro?

Many of its rules are written as conditions for "central assistance". It also says "All the metro rail projects will have to be governed by the Central Metro Acts." It is a policy, not an Act. We read no text that makes it binding on states.

This guide is general information, not legal advice. Laws, rules and court rulings change, and courts decide each case on its facts. Which law applies differs by project and by state. For advice on a real situation, speak to a lawyer. It draws on two Acts, a central policy and a PIB release. It also uses rulings of two courts and two news reports. Each is dated and credited. It takes no side between governments, agencies and residents.

Last checked 30 October 2026.

Sources

Accessed 30 October 2026. The tag shows how much of each source we read: in full, only in part (for example a paywalled or cut-off article), or not at all.

  1. Metro Railways (Construction of Works) Act, 1978 (Indian Kanoon; the copy says it "could not be verified"). Partly read Sections 1, 2, 6 to 10, 16, 32 and 39 read; the rest searched. The Schedule is not shown.
  2. National Highways Act, 1956 (Indian Kanoon; the copy says it "could not be verified"). Partly read Sections 1 to 3D read; sections 1 to 10 searched for "alignment" and "flyover".
  3. Metro Rail Policy 2017 (copy on the NCRTC website; no printed date). Read in full The ministry’s own copy did not open (error 404). This is not the ministry’s copy.
  4. Metro Rail Policy 2017 (copy on the Pune Metro website; the same file as the NCRTC copy). Read in full
  5. PIB, "Union Cabinet approves new Metro Rail Policy; Focus on compact urban development, cost reduction and multi-modal integration", 16 August 2017. Partly read The first part of the release read.
  6. Supreme Court, national highway widening, (2011) 12 SCC 69 (Indian Kanoon), 21 February 2011. Partly read The facts, the objections and the court’s conclusions read.
  7. Bombay High Court (division bench), Mumbai Metro Line 4, 2023:BHC-OS:2159-DB (Indian Kanoon), 30 March 2023. Partly read The facts, the Act’s reach, the land-acquisition holding and the orders read.
  8. Newsband, "Thane ring metro route to stay, stations may shift", 24 September 2026. Read in full
  9. Hindustan Times, "Shimla: Justify dropping surface highway plan for twin tunnel project, HC tells NHAI", 30 October 2026. Read in full
  10. Free Press Journal, Loksatta and Mumbai Live on the Thane march of 4 October 2026, as credited by our Thane report. Not read Not opened for this guide. The line is given only as our live report states it.
  11. Hindustan Times reports of September 2026 and PTI, as credited by our Sanjauli report. Not read Not opened for this guide. The lines are given only as our live report states them.
  12. The Himachal Pradesh High Court order reported by Hindustan Times on 30 October 2026. Not read Its words are given only as Hindustan Times quotes them.
  13. Notifications extending the 1978 Act; its rules and Schedule; the 2013 land law; state metro, planning and municipal laws. Not read Points from these are given only as the sources above report them, or dropped.
  14. India Code copies of both Acts; a dictionary entry for "alignment" (the page returned an error). Not read

Spotted an error, or a source we missed? Email a correction with the source that shows it. See how we handle corrections. Back to top