Short answer
NCERT’s Class 10 textbook says dams built for uses such as irrigation, electricity, water supply and flood control are "now referred to as multi-purpose projects". No law we read defines the term, and not every dam serves all these uses. Clearance and dam-safety rules apply by size and category.
This guide is general information, not legal advice. It describes what official texts say about multipurpose river valley projects and why people object to them. It does not tell anyone what to do. We read the texts on 26 October 2026.
What does "multipurpose river valley project" mean?
The Oxford Learner’s Dictionary defines multipurpose as "able to be used for several different purposes". For dams, the clearest description we read is in NCERT’s Class 10 geography textbook (Contemporary India II, chapter 3, Reprint 2026-27). It says:
Today, dams are built not just for irrigation but for electricity generation, water supply for domestic and industrial uses, flood control, recreation, inland navigation and fish breeding. Hence, dams are now referred to as multi-purpose projects where the many uses of the impounded water are integrated with one another.
NCERT gives two examples. It says the Bhakra-Nangal project’s water "is being used both for hydel power production and irrigation". It says the Hirakud project "integrates conservation of water with flood control".
The Oxford Learner’s Dictionary defines a reservoir as "a natural or artificial lake where water is stored before it is taken by pipes to houses, etc."
No text we read defines the term. We searched four texts. They are the Dam Safety Act, 2021, the EIA Notification, 2006, the National Water Policy, 2012 and the Central Water Commission’s 2017 guidelines. None defines "multipurpose project" in the parts we read. The 2017 guidelines use it in their title: "Guidelines for Submission, Appraisal and Acceptance of Irrigation and Multipurpose Projects, 2017".
What jobs can one dam do?
The Central Water Commission (CWC) describes its own work this way:
The Commission is entrusted with the general responsibilities of initiating, coordinating and furthering in consultation of the State Governments concerned, schemes for control, conservation and utilization of water resources throughout the country, for purpose of Flood Control, Irrigation, Navigation, Drinking Water Supply and Water Power Development.
The CWC’s page for children explains what dams do. It says: "Dams store water for irrigation, drinking water, making electricity, and for recreation. Dams can also help control flooding." It adds that the stored water "can be used to generate electricity or to supply water for homes and industries, for irrigation, or for navigation."
The same page says one use can follow another: "The water after generation of electricity can be used for irrigation and drinking purposes."
Is every dam a multipurpose project?
No source we read says so. The CWC’s page for children says: "Some dams are built specifically to produce hydroelectric power, which is electricity generated from water."
The National Dam Safety Authority’s National Register of Specified Dams (April 2025) has a "Purpose" column for each dam. Its list of short forms includes "Irrig." for irrigation and "Hydro." for hydropower. In the rows we read, entries include "Irrig.", "Hydro." and "Multipurpose". We did not count them.
NCERT’s line that dams "are now referred to as multi-purpose projects" is the textbook’s description. The register lists a purpose dam by dam.
Does a dam always control floods?
The sources we read do not agree. The CWC says: "Dams can also help control flooding." NCERT’s textbook says:
Ironically, the dams that were constructed to control floods have triggered floods due to sedimentation in the reservoir. Moreover, the big dams have mostly been unsuccessful in controlling floods at the time of excessive rainfall.
The National Water Policy, 2012 has a line on running reservoirs during floods. Paragraph 10.5 says:
Operating procedures for reservoirs should be evolved and implemented in such a manner to have flood cushion and to reduce trapping of sediment during flood season.
The policy does not define "flood cushion" in the parts we read, so we do not explain it.
What does the national water policy say?
The National Water Policy, 2012 is a policy, not a law. We read an archived copy of the Ministry of Water Resources PDF. Paragraph 9.7 says:
All water resources projects, including hydro power projects, should be planned to the extent feasible as multi-purpose projects with provision of storage to derive maximum benefit from available topology and water resources.
Paragraph 3.4 says "all multipurpose projects over water bodies should keep navigation in mind right from the planning stage." Our guide to water priority covers what the policy says about drinking water and irrigation.
Which laws apply to a dam project?
The two texts below set their tests by size, height and category. Neither uses the word multipurpose in the parts we read. Each has its own scope.
| Text | What it is about | When it applies |
|---|---|---|
| EIA Notification, 2006 (July 2026 consolidated copy) | "prior environmental clearance" | Item 1(c), "River Valley and hydro-electric Projects": listed sizes of hydropower and irrigation projects. |
| Dam Safety Act, 2021 | "surveillance, inspection, operation and maintenance of the specified dam" | A "specified dam": one above fifteen metres, or ten to fifteen metres meeting a listed condition. |
Environmental clearance. Paragraph 2 of the EIA Notification says listed projects "shall require prior environmental clearance". It must come "before any construction work, or preparation of land by the project management except for securing the land, is started on the project or activity". EIA stands for environment impact assessment.
We read the Ministry of Environment’s copy marked "AS AMENDED UP TO JULY 2026". Its disclaimer says office memoranda are not included. It also says: "In case there is a discrepancy, then the principal notification read along with the amendment issued in the gazette of India shall prevail". In that copy, item 1(c) reads:
- Hydropower, Category A: "≥ 100 MW hydroelectric power generation".
- Hydropower, Category B: "≥ 25 MW and < 100 MW hydroelectric power generation".
- Irrigation, Category B only: "> 2000 ha. of culturable command area". A table under it marks minor systems (≤ 2000 ha) "Exempted". Medium systems are "(B2 category)". Major systems (≥ 10,000 ha) are "(B1 category)".
Item 1(c) sets its hydropower thresholds at 25 MW and 100 MW. A note says pump storage projects that meet three listed criteria "shall be appraised as B2 category irrespective of power generation capacity". We did not check office memoranda. The notification does not define "culturable command area" in the parts we read.
Paragraph 2 sends Category A to the Central Government and Category B to state authorities. A note to item 1(c) says "Category ‘B’ river valley projects falling in more than one state shall be appraised at the central Government Level." Another says "Irrigation projects involving Inter-State issues shall be appraised at Central level without change in category."
A General Condition also applies. It moves a Category B project to the Central level, as Category A, if it lies within 5 km of listed areas. These include notified Protected Areas and inter-State boundaries. For river valley projects, it says "the appraisal shall be made at Central level even if located within 10 km." A proviso says the distance from inter-State boundaries "can be reduced or completely done away with by an agreement" between the States or Union Territories concerned. That applies where the activity is not within 5 km or 10 km of the listed Protected Areas, Critically Polluted areas or Eco-sensitive areas.
Clearance for river valley projects is valid for "thirteen years", paragraph 9(ii)(a) says. A proviso allows an extension "by a maximum period of two years in the case of River Valley projects", if applied for within the validity period. Our EIA public hearing guide covers the hearing stage. Our forest clearance guide covers forest land.
Dam safety. The Dam Safety Act, 2021 is about keeping specified dams safe. Section 4(e) says "dam" means:
any artificial barrier and its appurtenant structure constructed across rivers or tributaries thereof with a view to impound or divert water which also include barrage, weir and similar water impounding structures but does not include- (a) canal, aquaduct, navigation channel and similar water conveyance structures; (b) flood embankment, dike, guide bund and similar flow regulation structures;
Section 4(x) defines a "specified dam". It covers a dam "above fifteen metres in height, measured from the lowest portion of the general foundation area to the top of dam". It also covers one "between ten metres to fifteen metres in height" that meets at least one of five conditions. These cover crest length, reservoir capacity, flood discharge, foundation problems and unusual design. The Indian Kanoon copy prints this clause out of order. We checked it against the Bill as passed by the Lok Sabha in 2019.
We read no section of the Act that approves a dam project. On construction, section 26(6) says:
The construction of any specified dam or the alteration or enlargement of any existing specified dam shall be undertaken with the approval of such competent authority, as may be specified by notification by the Central Government or the State Government, as the case may be.
Section 27(2) says that before a reservoir is first filled, the State Dam Safety Organisation "shall inspect or cause to be inspected the specified dam". A report follows, "duly certifying the fitness of dam for filling".
When did the Act start? We did not read the Act’s commencement notice. The Indian Kanoon copy we read is headed "Not commenced", while its footnote names a notification. So we give no start date.
Why do people object to multipurpose projects?
NCERT’s textbook lists reasons. It says:
In recent years, multi-purpose projects and large dams have come under great scrutiny and opposition for a variety of reasons. Regulating and damming of rivers affect their natural flow causing poor sediment flow and excessive sedimentation at the bottom of the reservoir, resulting in rockier stream beds and poorer habitats for the rivers’ aquatic life. Dams also fragment rivers making it difficult for aquatic fauna to migrate, especially for spawning. The reservoirs that are created on the floodplains also submerge the existing vegetation and soil leading to its decomposition over a period of time.
Wiktionary defines submergence as "The act of submerging or the state of being submerged; submersion."
NCERT goes on: "It was also observed that the multi-purpose projects induced earthquakes, caused water-borne diseases and pests and pollution resulting from excessive use of water." These are the textbook’s words. We did not check them against other studies.
The CWC’s page for children says this about hydropower plants:
However the hydropower plants can be constructed only at limited places, require large investment and time. They submerge the large area and cause social and environmental problems. The Government rehabilitates the villagers whose land is submerged.
The last sentence is the CWC’s claim. Our dam-displacement guide quotes what the 2013 land law says on rehabilitation before submergence. Our land acquisition guide covers compensation.
How is this different from river interlinking, a DPR or a water dispute?
These are related but separate topics. Each has its own guide.
- River interlinking. One link project can include a multipurpose project. The Press Information Bureau (PIB) said on 8 December 2021 that the Ken-Betwa link involves the "Bina Complex Multipurpose Project", among other works. Our river-interlinking guide explains the link plan.
- Detailed project report (DPR). The CWC’s 2017 guidelines say they "are applicable to major, medium irrigation and multi-purpose projects on inter-State rivers or their tributaries." Our guide to detailed project reports explains the steps.
- Water disputes. NCERT says the Krishna-Godavari dispute concerns "the diversion of more water at Koyna by the Maharashtra government for a multipurpose project." Our guide to interstate river water disputes explains how such disputes are decided.
What do recent news reports say?
These are news reports, not our reports. Each line keeps the outlet’s own words and date.
Kishau project (Tons river, Himachal Pradesh-Uttarakhand border). The New Indian Express reported on 15 September 2026 that six states signed a Memorandum of Understanding with the Centre. It said: "The long-pending multipurpose project is expected to provide irrigation, electricity, drinking and industrial water and help rejuvenate the Yamuna. The project will now be placed before the Union Cabinet for approval." It also said: "The Centre will bear 90 per cent of the cost of its water component." We did not check for a later Cabinet decision.
Kamala project (Arunachal Pradesh). ANI reported on 9 April 2026 on the 1720 MW Kamala Hydro Electric Project. It said the Cabinet Committee on Economic Affairs approved an investment of "Rs 26,069.50 crore". ANI said the project would "provide flood moderation benefits in the Brahmaputra valley, a release said." It said the Government of India "will provide Rs 4,743.98 crore as budgetary support towards the flood moderation component". We did not read the release itself.
Ken-Betwa link (Madhya Pradesh and Uttar Pradesh). PIB’s release of 8 December 2021 said: "The project will provide an annual irrigation of 10.62 lakh ha, drinking water supply to a population of about 62 lakhs and also generate 103 MW of hydropower and 27 MW solar power." These were the Government’s figures on that date.
Where can you see a dam’s listed purpose?
The National Register of Specified Dams, published by the National Dam Safety Authority, lists a purpose for each dam in it. The April 2025 edition is on the CWC website. Its disclaimer says it "is prepared for general information purposes". It also says "users should verify the information from the SDSO/Dam Owner/Authority concerned." SDSO stands for State Dam Safety Organisation.
What could we not confirm?
- An official definition of "multipurpose project". We found none in the texts we read.
- The Dam Safety Act’s start date. We did not read its commencement notice.
- Whether office memoranda after the July 2026 copy change item 1(c). The Gazette text prevails over that copy.
- NCERT’s statements on earthquakes and disease. We did not check them against other studies.
- Whether a later water policy has replaced the 2012 policy. We did not check.
- The Kishau project’s Cabinet decision and the release ANI quoted on Kamala.
Examples from our reports
We link one live report that describes a multipurpose project. The line keeps the page’s own words and outlets, as on its update date. See also: our dam-displacement guide, our river-interlinking guide and our EIA public hearing guide.
- Kulsi dam protests on the Assam-Meghalaya border: updated 26 October 2026. The page describes the Kulsi Multipurpose Project as "a 55 MW hydropower and irrigation project" at Ukiam. It says the project "would irrigate about 26,000 hectares", according to the Union Ministry of Jal Shakti "as cited by Hub Network and other outlets".
Frequently asked questions
Is a multipurpose project the same as a dam?
Not every dam is called one. NCERT says dams "are now referred to as multi-purpose projects". The CWC says "Some dams are built specifically to produce hydroelectric power". The NDSA register lists a purpose for each dam.
Does every dam project need environmental clearance?
The EIA Notification lists which projects need it. In the July 2026 copy we read, item 1(c) sets hydropower thresholds at 25 MW and 100 MW. Irrigation is listed above 2,000 hectares of culturable command area. A note says pump storage projects meeting three criteria "shall be appraised as B2 category irrespective of power generation capacity". It marks minor irrigation "Exempted". The Gazette text prevails over that copy.
Does the Dam Safety Act approve new dams?
We read no section that does. Section 26(6) says construction "shall be undertaken with the approval of such competent authority, as may be specified by notification". The Act is about the safety of specified dams. This is general information, not legal advice.
Do dams stop floods?
The sources differ. The CWC says "Dams can also help control flooding." NCERT says big dams "have mostly been unsuccessful in controlling floods at the time of excessive rainfall."
What happens to people whose land goes under water?
The CWC says: "The Government rehabilitates the villagers whose land is submerged." That is the CWC’s claim. Our dam-displacement guide quotes the 2013 land law on rehabilitation.
This guide is general information, not legal advice. It describes NCERT’s textbook, CWC and NDSA pages and the 2012 water policy. It also uses the EIA Notification, the Dam Safety Act, a PIB release, two news reports and one of our live reports. Each source is dated where it gives a date, and credited. It takes no side on any government, company, party or group.
Last checked 26 October 2026.
Sources
Accessed 26 October 2026. The tag shows how much of each source we read: in full, only in part (for example a paywalled or cut-off article), or not at all.
- NCERT, Contemporary India II (Class 10 geography), chapter 3, "Water Resources", Reprint 2026-27. Read in full Read by the writer.
- Central Water Commission, "Welcome to Central Water Commission". Read in full Read by the writer. Footer: last updated 26-10-2026.
- Central Water Commission, "Information For Kids". Partly read Dams and hydropower sections read by the writer. Footer: last updated 26-10-2026.
- Central Water Commission, "Guidelines for Submission, Appraisal and Acceptance of Irrigation and Multipurpose Projects, 2017", 2017. Partly read Title page, preface and paragraph 1.5 read by the writer; searched for a definition.
- National Dam Safety Authority, "National Register of Specified Dams", April 2025. Partly read Disclaimer, short forms and sample tables read by the writer. No counts taken.
- Ministry of Water Resources, "National Water Policy (2012)" (Internet Archive copy, saved 5 February 2023), 2012. Partly read Paragraphs 3.4, 9.7 and 10.5 read by the writer.
- Ministry of Environment, Forest and Climate Change, Environment Impact Assessment Notification 2006 and subsequent amendments, "AS AMENDED UP TO JULY 2026" (Parivesh copy), July 2026. Partly read Disclaimer, paragraph 2, paragraph 9(ii)-(iii), Schedule item 1(c) and the General Condition read by the writer. The Gazette text prevails over this copy.
- The Dam Safety Act, 2021 (Act 41 of 2021) (Indian Kanoon copy). Partly read Read by the writer: header, long title, sections 1(3), 4(e), 4(w), 4(x), 26(6), 27(2) and footnote 1. The copy says its content "could not be verified".
- The Dam Safety Bill, 2019, as passed by Lok Sabha (PRS copy), 2019. Partly read Clause 4(x) read by the writer, to check the layout of the Act copy’s section 4(x).
- Press Information Bureau, "Cabinet approves Ken-Betwa Interlinking of Rivers Project", 8 December 2021. Read in full Read by the writer.
- The New Indian Express, "Kishau Dam project clears eight-year hurdle as six states sign MoU with Centre", 15 September 2026. Read in full Read by the writer from the page source.
- ANI, "CCEA approves investment for development of 1720 MW Kamala Hydroelectric project in Arunachal", 9 April 2026. Read in full Read by the writer.
- Oxford Learner’s Dictionaries, "multipurpose". Read in full Read by the writer.
- Oxford Learner’s Dictionaries, "reservoir". Read in full Read by the writer.
- Wiktionary, "submergence". Read in full Read by the writer.
- All India Protest, Kulsi dam protests on the Assam-Meghalaya border (our live report), updated 26 October 2026. Read in full Used for the example line only.
- Hub Network and other outlets on the Kulsi project. Not read Named only as our live report credits them; not opened for this guide.
- The Dam Safety Act’s commencement notification (S.O. 5422(E)); the EIA Notification’s Gazette originals and later office memoranda; the release ANI quoted on Kamala. Not read Not opened.
Spotted an error, or a source we missed? Email a correction with the source that shows it. See how we handle corrections. Back to top